In the spring of 2016, Davidson and Jones contracted with IQ Contracting to perform repairs to the multi-level parking structure that were identified in the report developed by IQ Engineering. Repairs included the following:
Overhead concrete beam repairs
Elevated slab repairs
Column Repairs
Epoxy Injection
CFRP Installation
Sealant removal and replacement
EXPJT removal and replacement
Vehicular Deck Coating System
Several means and methods were used to complete these repairs such as shotcrete, form and pour and had applied methods. The project was completed in early spring of 2017.